Completion of the remaining works of the second Yazd pipeline project and Arsanjan-Kerman pipeline
Description
Completion of the remaining works of the second Yazd pipeline project and Arsanjan-Kerman pipeline
Type
Construction of fencing of three valve stations of "42 Arsanjan / Kerman" pipeline project
Project size
Three valve stations of the 42 Arsanjan / Kerman pipeline project with an approximate length of 19 km
Employer
Iran Gas Engineering and Development Company
Year of implementation
2008
Project description
Procurement of materials, transportation, construction and installation of one-meter wide human doors and 5-meter-wide iron car doors, each according to the details of the doors in the contract drawings.
Preparation of materials, transportation, construction and installation of connecting parts of fencing bases of iron sheet for Expansion joint in the number of 80 bases, in each base three connections are made with bolts and nuts
Preparation of materials and execution of complete oil paint (crown) on the fence surface except galvanized barbed wire cases
Preparation of materials and installation of six rows of first-class galvanized barbed wire along the entire length of the fence, which is executed on the doors of the man and the car, as well as the ring barbed wire between the opening space of six rows of longitudinal barbed wire according to the contract drawings.
Preparation, transportation, distribution and leveling of the base rough mixture with a grain size limit of 5 cm in diameter for the station area + 00 km with a thickness of 15 cm in an area of 7389 square meters without taking into account the fence wall and the transmitter foundation Inside the station and the guard road around it
Preparation, transportation and leveling of 10 cm thick reduction sand for the area inside the station with an area of 100 * 100 square meters without taking into account the surface of the fence wall with a width of 46 cm and concreting done in three stations
Preparing, transporting, distributing, leveling and pounding the river mixture for protected roads around three stations with an area of 9975 square meters and the entrance route of the station
Preparation of materials and construction of 10 pig signal ponds, preparation of materials and construction of one drainage pond D.P
Collecting and transporting pipes and surplus goods along the pipeline route from 0 to 177 km