Water transmission line construction project from Susangard water treatment plant to Hamidiyeh, Bostan, Hoveyzeh and Rafi cities
Description
Water transmission line construction project from Susangard water treatment plant to Hamidiyeh, Bostan, Hoveyzeh and Rafi cities
Type
Construction of water transmission line
Project size
Construction of water transmission line from Susangard water treatment plant with a length of 90 km
Employer
Khuzestan Water and Power Organization Company
Year of implementation
2009
Project description
The subject of the agreement is the construction of a water transmission line from the Susangard water treatment plant to the cities of Hamidiyeh, Bostan, Hoveyzeh and Rafi
Piping with asbestos cement pipe with a diameter of 150 mm
Piping with welded steel pipe with a diameter of 500 mm on the existing bridge of Bostan water supply line
Construction of water transmission line from Susangard water treatment plant to Hamidiyeh, Bostan, Hoveyzeh and Rafi cities, including piping with GRP pipes with a diameter of 700, 600, 500, 400, 800 mm, a total length of about 90 km with fittings and valves Relevant, the construction of the valve pool and the service road required at a distance of about 55 km west of Ahvaz, along with the operation of equipping and dismantling the workshop in accordance with the drawings and technical specifications.